Passing the exam is not easy, it requires preparation and discipline. Starting with 10 questions on study days up to 50 or 60 questions. The “secret sauce” is with the question patterns Regards Gabor Stramb
Correct answer is D.
One of the mandatory standards for a project manager is to show respect to others by holding them in high regard. A project manager must respect others’ viewpoints.
A project manager need not develop a complete WBS during the initial stages of planning.
In long projects, the WBS can be developed partially and can be extended as more details become known later; this approach is known as rolling wave planning.
The project manager should explain rolling wave planning to the resource. Ignoring the resource’s comments or removing the resource are not appropriate responses.
Correct answer is D.
One of the mandatory standards for a project manager is to show respect to others by holding them in high regard. A project manager must respect others’ viewpoints.
A project manager need not develop a complete WBS during the initial stages of planning.
In long projects, the WBS can be developed partially and can be extended as more details become known later; this approach is known as rolling wave planning.
The project manager should explain rolling wave planning to the resource. Ignoring the resource’s comments or removing the resource are not appropriate responses.