Test your knowledge with this question.
Iβm personally interested in which answer you picked π
Letβs have a look.

Correct answer is B.
The stakeholder influence is highest at the start of the project and decreases as the project progresses towards completion.This is due to the fact that risk and uncertainty are greatest at the start of the project.Β