CAPM Mock Exam Question

Test your knowledge with this question.

I’m personally interested in which answer you picked πŸ™‚

Let’s have a look.

ANSWER

Correct answer is C.

The WBS is a deliverable oriented hierarchical decomposition of the work to be accomplished by the project team to accomplish project objectives.