CAPM Mock Exam Question

Test your knowledge with this question.

I’m personally interested in which answer you picked πŸ™‚

Let’s have a look.

ANSWER

Correct answer is B.

Validate Scope differs from Control Quality in that Validate Scope is primarily concerned with the acceptance of the deliverables, whereas Control Quality is primarily concerned with meeting the quality requirements specified for the deliverables.