CAPM Mock Exam Question

Come and try this question.

I help you make progress and pass the CAPM exam.

But for now try to answer this question below.

Scroll down for correct answer

ANSWER

Correct answer is D.

When risks cannot be handled or managed in a project, it is advisable to accept them.In this scenario, your team is unable to devise a suitable response strategy.Hence, risk acceptance is the correct strategy to employ.

Leave a Reply