Come and try this question.
I help you make progress and pass the CAPM exam.
But for now try to answer this question below.
Scroll down for correct answer

ANSWER
Correct answer is C.
This is an example of avoidance. It involves changing the project management plan to “eliminate” the threat posed by an adverse risk, isolating the project objectives from the risk’s impacts, or relaxing the objective that is in jeopardy, such as by extending the schedule or reducing scope. Transference involves shifting the negative impact of a threat along with the ownership of the response. Mitigation implies a reduction in the probability and impact of an adverse risk. Postponement is not a valid strategy since it does not address the risk.