Test your knowledge with this question.
I’m personally interested in which answer you picked 🙂
Let’s have a look.

ANSWER
Correct answer is C.
This is an example of avoidance. It involves changing the project management plan to “eliminate” the threat posed by RACI chart is not a data analysis technique used during quantitative risk analysis. Rest of the choices are valid techniques for data analysis.