CAPM Mock Exam Question

Have you been preparing for the exam for months? Stuck with the preparation?

Or considering quitting and doing it in 6 months time?

I help you make progress and pass the CAPM exam.

But for now try to answer this question below.

Scroll down for correct answer

ANSWER

Correct answer is D.

Upper level WBS components are decomposed into more easily managed elements and can be process-or product-oriented.The lowest level of the WBS is the work packages. The project activities are obtained by further decomposing the work packages.The activities become a part of the project schedule and not the WBS.