Test your knowledge with this question.
Iβm personally interested in which answer you picked π
Letβs have a look.

ANSWER
Correct answer is A.
The project manager, a team member or the project sponsor do not typically perform the role of lead negotiator on procurements. Due to the legal nature of the contractual relationship involved, a legal representative or a procurement administrator is involved.