Test your knowledge with this question.
Iβm personally interested in which answer you picked π
Letβs have a look.

ANSWER
Correct answer is D.
Risk reassessment is performed as part of the Monitor Risks process. Such project risk reassessments should be regularly scheduled and may result in the closure of outdated risks.