CAPM Mock Exam Question

Test your knowledge with this question.

I’m personally interested in which answer you picked πŸ™‚

Let’s have a look.

ANSWER

Correct answer is B.

Since John is in the execution phase and stakeholders are requesting project information, he must respond through the Manage Communications process. The communications management plan, organizational process assets and work performance reports are inputs to this process. Shawn can use any of these documents to respond to their requests. The project’s business case is not of much help at this stage.

Leave a Reply