CAPM Mock Exam Question

Come and try this question.

I help you make progress and pass the CAPM exam.

But for now try to answer this question below.

Scroll down for correct answer

ANSWER

Correct answer is A.

This is an example of a constraint. Constraints are factors that can limit the project management team’s options.An organizational mandate requiring that a certain part of the team operate from a different location to obtain cost savings is a constraint that the project management team needs to incorporate into their planning.