CAPM Mock Exam Question

Test your knowledge with this question.

I’m personally interested in which answer you picked 🙂

Let’s have a look. 


ANSWER

Correct answer is B.

The project scope is measured against the project scope baseline, which consists of the project scope statement, its associated WBS and the WBS dictionary.