Test your knowledge with this question.
I’m personally interested in which answer you picked 🙂
Let’s have a look.Â

ANSWER
Correct answer is B.
The project scope is measured against the project scope baseline, which consists of the project scope statement, its associated WBS and the WBS dictionary.