Come and try this question.
I help you make progress and pass the CAPM exam.
But for now try to answer this question below.
Scroll down for correct answer

ANSWER
Correct answer is D.
The accuracy of Activity Duration estimates can be improved by considering the amount of risk in the original estimate.
The three types of estimates on which three-point estimates are based are: Most likely, Optimistic, and Pessimistic.
An Activity Duration can be estimated using values derived from these three estimated durations.