CAPM Mock Exam Question

Have you been preparing for the exam for months? Stuck with the preparation?

Or considering quitting and doing it in 6 months time?

I help you make progress and pass the CAPM exam.

But for now try to answer this question below.

Scroll down for correct answer

ANSWER

Correct answer is C.

A planning package is a work breakdown structure component below the control account and above the work package with known work content but without detailed schedule activities.[PMBOK 6th edition, Page 161] [Project Stakeholder Management]