Challenging questions for the PMP Exam – 01 Posted on October 11, 2019May 1, 2020 by gstramb The project manager stated that he expected the total project to cost $4.500. Which of the following terms does this statement best describe? Estimate at completion – EACestimate to complete – etcactual cost – acvariance at completion – vac
and the answer is: Estimate to complete!