Challenging questions for the PMP Exam – 02

Integration Management

You are beginning a new project. When should you use the Perform Integrated Change Control process?

A. Throughout the entire project

B. Only when closing out the project

C. Only after the project is completely funded

D. Only after the project scope is clearly defined

Leave a Reply