Correct answer is B
Inspections and audits required by the buyer and supported by the supplier, if specified in the procurement contract, can be conducted during execution of the project to verify compliance in the seller’s work processes or deliverables. [PMBOK 6th edition, Page 498] [Project Procurement Management]