Correct answer is D – A risk reassessment is a technique that involves reevaluating project risks and identifying new risks that arise as the project moves forward.
These risks are evaluated and placed in the risk register. The PMBOK recommends conducting risk reassessments during team meetings as a part of the Monitor Risks process.