gstramb Post authorJuly 23, 2022Log in to Reply Correct answer is C. Rolling wave planning. Rolling wave planning is a form of progressive elaboration and is used when the project management team does not have enough information for a phase or deliverable that will occur far into the future.
Correct answer is C.
Rolling wave planning. Rolling wave planning is a form of progressive elaboration and is used when the project management team does not have enough information for a phase or deliverable that will occur far into the future.