PMP Exam Prep Question

Join PRO Study Group and be part of the community.
Comment your answer below.
Cheers
Gabor

1 thought on “PMP Exam Prep Question

  1. gstramb Post author

    Correct answer is B. Solving the question using elimination method:
    option A: dependency determination and integration is when you find relationship between activities. So this option is irrelevant.
    option B: critical path is the path where you don’t have leverage to miss any schedule activity. This is what is asked in the question.
    option C: precedence diagram talks about the relationship between activities. So this option is irrelevant.
    option D: irrelevant to this question.

Leave a Reply