Correct answer is B. Solving the question using elimination method:
option A: dependency determination and integration is when you find relationship between activities. So this option is irrelevant.
option B: critical path is the path where you don’t have leverage to miss any schedule activity. This is what is asked in the question.
option C: precedence diagram talks about the relationship between activities. So this option is irrelevant.
option D: irrelevant to this question.