PMP Exam Prep Question

“I read the book, completed the course and I’m simply OVERWHELMED!”
If this is YOU.
I’m here to solve this problem for You.

Join Group Coaching Calls(EAME and US timezone) and be par of the community.
Comment your answer below.
Thanks
Gabor Stramb

1 thought on “PMP Exam Prep Question

  1. gstramb Post author

    Correct answer is C.
    Explanation Leveling resources generally extends the schedule.
    Monte Carlo analysis does not directly address the constraints of this situation.
    To compress the schedule, you could either crash or fast track.
    However, the situation says that the network diagram cannot change.
    This eliminates fast tracking, which leaves crashing the project as the best answer.

Leave a Reply