Correct answer is C.
Explanation Leveling resources generally extends the schedule.
Monte Carlo analysis does not directly address the constraints of this situation.
To compress the schedule, you could either crash or fast track.
However, the situation says that the network diagram cannot change.
This eliminates fast tracking, which leaves crashing the project as the best answer.