Correct answer is C.
Regardless how bad the situation is, send inaccurate project reports is never an option.
Further ignoring the negative stakeholders is not recommended.
Sending periodic project updates will help but the best way to reduce the negative bias towards the project is to involve the negative stakeholders in project decisions so they get a sense of ownership.