PMP Exam Prep Question

Good Morning
Let’s finish this week strong 🙂
Comment your answer below.
Also
Join the PRO Study Group NOW

1 thought on “PMP Exam Prep Question

  1. gstramb Post author

    Correct Answer is B.
    All the requirements identified in Collect Requirements may not be included in the project as the Define Scope process selects the final project requirements from the requirements documentation developed during the Collect Requirement process.
    Analyzing the objection and determining if the requirements were deliberately dropped during the Define Scope process is the best response.