PMP Exam Prep Question

Today is Saturday, so it is Gameday
Let’s finish this week strong
Comment your answer below.
Join
PRO Study Group NOW

1 thought on “PMP Exam Prep Question

  1. gstramb Post author

    Correct answer is A.
    One of the Agile value is “working software over comprehensive documentation”.
    This implies that agile teams prefer working software over comprehensive documentation.
    The documentation in agile is just good enough to meet the needs and nothing extra is taken care of.
    As a scrum master, you must understand the need for the documentation and also to what level it is required.
    If the documentation in question is regarding some mandatory things or regulatory compliance, then the team must discuss how to best address it. But, nothing in the question indicates that.