PMP Exam Prep Question Posted on March 4, 2022 by gstramb Good morning,I hope you are ready and fresh for the next challenging question?Comment your correct answer below.
gstramb Post authorMarch 5, 2022Log in to Reply Correct Answer is D. Resource Leveling can cause the projects’ critical path to change, while Resource Smoothing doesn’t alter the project’s critical path.
Correct Answer is D. Resource Leveling can cause the projects’ critical path to change, while Resource Smoothing doesn’t alter the project’s critical path.