1 thought on “PMP Exam Question

  1. gstramb Post author

    Correct answer is C. A cost-reimbursable contract gives the project flexibility to redirect a seller whenever the scope of work cannot be precisely determined at the start of the project and needs to be altered, or when high risks may exist in the effort.