1 thought on “PMP Exam Question – Communication Management

  1. gstramb Post author

    Correct answer is A.
    The question is asking for a tool and technique that is not part of the Manage Communications process.
    Communication requirements analysis is a tool and technique of the Plan Communications Management process and not the Manage Communications process.
    PMBOK 6th edition, page 379.