  1. Stramb Gabor

    Correct answer is D.
    The correct response is Negotiation. This is done on many projects.
    The project management team may need to negotiate with functional managers to ensure that the team receives appropriately competent staff in the required time frame.
    The project management team may also need to negotiate with other project management teams. PMBOK, Page 332.