Correct Answer is C.
This technique is known as simulation. Project simulations use computer models and estimates of risk (usually expressed as a probability distribution of possible costs or durations at a detailed work level) and are typically performed using Monte Carlo analysis.
PMBOK Page 213 – Project Schedule Management.
Correct Answer is C.
This technique is known as simulation. Project simulations use computer models and estimates of risk (usually expressed as a probability distribution of possible costs or durations at a detailed work level) and are typically performed using Monte Carlo analysis.
PMBOK Page 213 – Project Schedule Management.