PMP Exam Question – Schedule Management

A technique that calculates multiple project durations with different sets of activity assumptions and variables is:

A. Process Analysis

B. Theoretical Analysis

C. Simulation

D. Effect Analysis

Join our Remote PMP Study Group Today

1 thought on “PMP Exam Question – Schedule Management

  1. Stramb Gabor

    Correct Answer is C.
    This technique is known as simulation. Project simulations use computer models and estimates of risk (usually expressed as a probability distribution of possible costs or durations at a detailed work level) and are typically performed using Monte Carlo analysis.
    PMBOK Page 213 – Project Schedule Management.