Which technique is NOT commonly used to align the timing of activities with available resources?
A. Critical Path Method
B. Resource Leveling
C. Resource optimization
D. Resource Smoothing
1 thought on “PMP Exam Question – Schedule Management”
Leave a Reply
You must be logged in to post a comment.
Correct answer is A.
The critical path method is not a technique commonly used to align the timing of activities with available resources.
The critical path method is a technique used to establish a rough timeline fitting the project’s work activities within the deadlines defined in the scope statement.
PMBOK, Pages 210 and 211.