PMP Exam Question – Schedule Management

All the following are tools of the Control Schedule process except:

A. Parametric estimating

B. Critical Path Method

C. Schedule compression

D. Leads and lags

1 thought on “PMP Exam Question – Schedule Management

  1. Stramb Gabor

    Correct answer is A.
    Leads and lags, schedule compression and critical path method are tools in the Control Schedule process.
    Parametric estimating is not a tool of this process. PMBOK 6th edition, Page 222.