PMP Exam Question – Scope Management

Establishing control accounts for the work packages and a unique identifier from a code of accounts finalizes the WBS.

This provides a structure for hierarchical summation of:

A. Schedule and requirements information

B. Cost and requirements information

C. Cost and resource information

D. Scope, budget and schedule information

1 thought on “PMP Exam Question – Scope Management

  1. Stramb Gabor

    Correct answer is D.
    The WBS is finalized by establishing control accounts for the work packages and a unique identifier from a code of accounts.
    This provides a management control point for integrated scope, schedule and cost information.
    PMBOK Guide, page 161.