PMP Exam Question – Stakeholder Management Posted on March 27, 2020May 1, 2020 by gstramb A change log is an important input to the Manage Stakeholder Engagement process. Which process provides this input? A. Plan Communications Management B. Manage Communications C. Perform Integrated Change Control D. Monitor Communications
gstramb Post authorMarch 30, 2020Log in to Reply Correct Answer is C. Project change logs are an output of the Perform Integrated Change Control process. PMBOK 6th edition, Page 113.
Correct Answer is C.
Project change logs are an output of the Perform Integrated Change Control process.
PMBOK 6th edition, Page 113.