PMP Exam Question – Stakeholder Management

A change log is an important input to the Manage Stakeholder Engagement process. Which process provides

this input?

A. Plan Communications Management

B. Manage Communications

C. Perform Integrated Change Control

D. Monitor Communications

1 thought on “PMP Exam Question – Stakeholder Management

  1. gstramb Post author

    Correct Answer is C.
    Project change logs are an output of the Perform Integrated Change Control process.
    PMBOK 6th edition, Page 113.