PMP Exam Question – Stakeholder Management

Which of the following graphical techniques visually depict the product scope by showing a business system and how other systems interact with it?

A. Ishikawa diagram
B. Histogram
C. Influence diagram
D. Context diagram

1 thought on “PMP Exam Question – Stakeholder Management

  1. Stramb Gabor

    Correct Answer is D.
    A context diagram is a graphical technique that visually depicts the product scope by showing a business system and how other systems interact with it.
    The other choices are graphical techniques designed to achieve other objectives.
    PMBOK, Page 146.

Leave a Reply