PMP Exam Question – Integration Management

Which process is concerned with providing forecasts to update current cost information?
A. Monitor and Control Project Work
B. Project Management Information System
C. Close Project or Phase
D. Direct and Manage Project Work

1 thought on “PMP Exam Question – Integration Management

  1. Stramb Gabor

    Correct answer is A.
    During the Monitor and Control Project Work process, work performance data is gathered and passed to the controlling processes.
    The Monitor and Control Project Work process is responsible for keeping track of the all project’s measures, including cost.
    PMBOK 6th edition, Page 109.

Leave a Reply