PMP Exam – Schedule Management – Question 1

Question:

In which of the following scennarios would it be better to avoid using Analogous Estimating?

  • A. When the project team members have the needed expertise
  • B. When an accurate estimate is required
  • C. When a low value estimate is required
  • D. When the previous activities are similar in fact and not just appearance

1 thought on “PMP Exam – Schedule Management – Question 1

  1. Stramb Gabor

    Correct answer is B.
    Analogous estimating is typically a “cheap” option(cost effective) also less accurate.
    This technique should not be used when accurate estimate is required.