Question:
In which of the following scennarios would it be better to avoid using Analogous Estimating?
- A. When the project team members have the needed expertise
- B. When an accurate estimate is required
- C. When a low value estimate is required
- D. When the previous activities are similar in fact and not just appearance

Correct answer is B.
Analogous estimating is typically a “cheap” option(cost effective) also less accurate.
This technique should not be used when accurate estimate is required.