PMP Exam – Schedule Management – Question 2

Are you able to manage Schedule on your project? If so, this question will be easy for you.

Question:

You’re a newly appointed Project Manager of a critical IT project. Project is already started and you are in the process of preparing the project schedule. Which of the following answers precisely describe the right sequence of activities which you have to perform before you can start preparing project schedule?

  • A. Sequence Activities, Estimate Activity Durations, Define Activities
  • B. Sequence Activities, Estimate Activity Durations, Develop Schedule
  • C. Define Activities, Estimate Activity Durations, Sequence Activities
  • D. Estimate Activity Durations, Sequence Activities, Develop Schedule