While managing a project, you have included the product acceptance criteria in the Quality Management Plan. While reviewing your plan, a senior manager asks you to reconsider this. You then realize that what you did is incorrect. Where should you place the product acceptance criteria?
A. Project Charter
B. Change control process
C. Scope Verification Plan
D. Project Scope Statement

Correct answer is D.
Explanation – The project scope statement documents and addresses the characteristics and boundaries of the project and its associated products and services, as well as product acceptance criteria and scope control. PMBOK Guide Page 154.