Scope management is the process of defining what work is required and then making sure all of that work – and only that work – is done.
Let’s dive into more deeply.
Do you know the correct logical sequence of Scope Management?

Question:

What is the logical sequence of the Project Scope Management processes?

A. Create WBS, Collect Requirements, Define Scope, Validate Scope, and Control Scope

B. Define Scope, Collect Requirements, Create WBS, Validate Scope, and Control Scope

C. Plan Scope Management, Collect Requirements, Define Scope, Create WBS, Validate Scope, and Control Scope

D. Plan Scope Management, Collect Requirements, Define Scope, Validate Scope, Create WBS, and Control Scope

1 thought on “PMP Exam – Scope Management

  1. gstramb Post author

    The correct answer is C.
    Explanation: the logical sequence of the six scope management processes is:
    Plan Scope Management, Collect Requirements, Define Scope, Create WBS, Validate Scope and Control Scope.
    Source: PMBOK 6th edition, Page 129