    Correct answer is B.
    The primary function of a PMO is to support project managers in a variety of ways.
    This may include developing and managing project policies, coaching, mentoring, training, and oversight.
    This may also include management of resources that are shared across the projects.
    However, development of a detailed description of each project would be a responsibility of the project manager handling the project, not of the PMO.