Correct answer is A – The key stakeholders’ concerns and requests can never be disregarded. Since the communication management plan is flexible and it does not restrict Stanley from doing bi-weekly updates, Stanley must immediately accept the key stakeholders’ request. Since this is not impacting the communication management plan, there is no need to go through the formal change control process.
Correct answer is A – The key stakeholders’ concerns and requests can never be disregarded. Since the communication management plan is flexible and it does not restrict Stanley from doing bi-weekly updates, Stanley must immediately accept the key stakeholders’ request. Since this is not impacting the communication management plan, there is no need to go through the formal change control process.