We learn through practice. To master the craft of passing the exam you need to focus on the βrightβ thing.
Join my CAPM/PMP exam prep community.
Comment your answer below.
Regards
Gabor Stramb
Scroll Down to Check the correct answer π
CAPM Study Group / PMP Study Group β Each week on Tuesday and Wednesday
4 week & 8 weeks exam prep
https://www.buymeacoffee.com/pmpexamcoaching/extras
Join CAPM/PMP Study Group
https://projectcertifications.com/study-group/
Subscribe to my YouTube
https://www.youtube.com/c/Projectcertifications
Learn more: Agile Basics Course
https://www.udemy.com/course/agile-basics-for-capm-exam/
PMBOK7
Practice Drag & Drop β https://pmnotebooks.com/ref/GaborS/
Training β https://www.buymeacoffee.com/pmpexamcoaching/e/116629

Correct answer is B.
All the requirements identified in Collect Requirements may not be included in the project as the Define Scope process selects the final project requirements from the requirements documentation developed during the Collect Requirement process. Analyzing the objection and determining if the requirements were deliberately dropped during the Define Scope process is the best response.