  1. gstramb Post author

    Correct answer is D.
    The project manager should use the Iterative life cycle since project phases and activities will most probably be repeated as the project team’s understanding of the project and requirements increases. Further, since any project phase can only start once its previous phase has been completed, the phase-to-phase relationship should be sequential.